Citizen Charter

Citizen Charter

 

All the owners of the electrical installations are requested to get their installations (new & periodic) inspected by this Inspectorate as per Electricity Act, 2003.

Timeline for Electrical Fitness Certificate

1.

Scrutiny of application submitted for Electrical Fitness Certificate

Within 2 working day from the date of submission of application.

2.

Communication of Inspection Fees payable, if application found in order

Within 1 working day

3.

Verification of Inspection Fees deposited through web portal

Within 2 working days after payment of fees.

4.

Intimation of date of Inspection and conduct of site Inspection

Within 10 working days after date of verification of fees depoited

5.

Communication of shortcomings / defects, if any

Within 3 working days after inspection

6.

Issuance of Fitness Certificate

Within 3 working days after submission of satisfactory compliance report